Work centres represent places or equipment used for production. Operations describe the work and timing for a bill of materials.

Set up production routing

  1. Open Production → Work centres. Add the centre and review its capacity and cost per hour.
  2. Open the bill of materials and add the operations in the intended order. Select the work centre for each operation.
  3. Review the duration, waiting time, and cost fields shown by the form. Confirm the materials and outputs in the same bill.
  4. Use the bill of materials on a production order and review its requirements before confirming the order.

Example

Add mixing and packing as separate operations and assign each to the appropriate work centre. Check their planned times on the bill of materials.